Industrial engineering is concerned with designing, improving and installing integrated systems of people, materials and equipment. In a plant the techniques used most are work study, quality control, plant layout and material handling, value engineering, and operations research.
Work study splits into method study (process analysis, operation analysis and motion analysis) and work measurement: direct time study, work sampling, and predetermined data.
Work study is the core of IE
The industrial engineering technique that pays off most inside a plant is work study, and it splits in two. Method study covers process analysis, operation analysis and motion analysis. Work measurement covers direct time study, work sampling and predetermined standard data.
The order matters: improve the method first, then measure the time. Timing a job that is still done badly yields the standard time for a bad method, and that becomes the planning baseline for years.
The techniques of IE
The industrial engineering techniques used in a plant are:
- Work study
- Quality control
- Plant layout and material handling
- Value engineering
- Operation research
The principle of motion economy: use of the human body
- Both hands should begin and end their motions at the same time
- Both hands should not be idle at the same time, except during rest
- Arm motions should be symmetrical, in opposite directions, and made at the same time
- Hand and body motions should be of the lowest classification that will do the work
- Continuous curved motions are preferred to straight-line motions with sudden changes of direction
- Arrange the work so that it is easy to do and falls into a natural rhythm
- Arrange the work to suit the eyes, without hard staring or frequent changes of focus
The principle of motion economy: arrangement of the workplace
- Give tools and material a definite place, as close to the operator as possible, so they are easy to pick up
- Order the tools in the sequence in which the work uses them
- Finished pieces should be dropped rather than pushed away by hand
- The light on the work must be sufficient
- The chair and bench must be proportioned to the operator’s body
- The colour of the work area should not blend with the work itself, so as to reduce eye strain
The principle of motion economy: design of tools and equipment
- Work in which a hand holds the piece should be redesigned to use a jig or fixture instead
- Combine two tools into one wherever the two functions allow it
- Where the fingers do the work, distribute the load to suit the natural capacity of each finger
- In designing a handle, maximise the area of hand in contact with it, particularly where the work requires turning force
- Tools should be designed to save the operator’s effort: contact area on a turning tool, leverage on a lever
Work measurement
There are three methods of work measurement, and each yields a different kind of standard time. Direct time study gives a standard time for the person. Work sampling gives one for the person and the machine. Predetermined data gives one for the person.
Work sampling
Work sampling establishes the percentage of time spent on each step of a job, using statistics and random observation. One observer using work sampling can collect and record times for several workers or several machines at once, where one observer using direct time study can study and record only one worker.
Simple work sampling takes observations at regular intervals rather than from a random schedule. It is easier, and accurate enough to find which worker or which machine is working inefficiently, and to establish a better sequence of operations by analysing the results and reordering the method.
Direct time study
Direct time study is the technique of measuring the time and the rate of working for the elements of a job under stated conditions, and of analysing that data to establish the time a job should take at a defined level of performance. Before timing anything, be sure the method being used is already the right one.
Time study runs in eight steps:
- Collect and record all the data that can be had about the job, the operator and the surrounding conditions that bear on it
- Record the whole method, break the job into elements, and describe each element
- Examine the elements to be satisfied the best method is in use, then calculate the sample size to be timed
- Measure with a stopwatch and record the observed time for each element
- Assess the operator’s rate of working against the observer’s standard, using rating
- Convert the observed time into basic time
- Determine the allowances
- Arrive at the standard time for the job
5W-1H is used twice
The 5W-1H set (what, why, where, when, who, how) is normally used to find the cause of a problem. In work study it is used twice: once to describe what actually happens now, and a second time to challenge every answer just given.
The second pass is where improvement happens. The question is not how, but why here, why now, why this person, and the most productive of all, what happens if we simply stop doing it. Often the answer is nothing.
| Analysis | Leads to improving |
|---|---|
| Process analysis | The production process |
| Operation analysis | How the operator works |
| Motion analysis | The operator’s movements |
How to apply it on the floor
- Confirm the method is right before timing it, or you standardise the wrong method
- Apply 5W-1H to every step you doubt, before designing a new one
- Use work sampling when several machines or people must be observed at once
- Design the workstation to the principles of motion economy before considering new equipment
The mistakes we see most
- Timing people to pressure them rather than to find a better method
- Setting a standard time with no allowance for rest and fatigue
- Improving the operator’s motions without fixing a layout that forces the walking
Common questions
How does IE relate to TPM?
TPM makes the equipment reliable; IE makes the work around it efficient. They reinforce each other and are usually used together inside the focused-improvement pillar.
What is industrial engineering?
Designing, improving and installing integrated systems of people, materials and equipment. The techniques used most in a plant are work study, quality control, plant layout and material handling, value engineering, and operations research.
What does work study include?
Method study (process analysis, operation analysis and motion analysis) and work measurement (direct time study, work sampling and predetermined data).
Should we improve the method or time the job first?
Improve the method first, then measure the time. Timing a job that is still done badly yields the standard time for a bad method, and that becomes the planning baseline for years.